Status of Each Pumping Plant & Lateral
Updated April 10, 2025 by Jennifer Hickenbottom, Bureau of Reclamation

Lateral 11.8
Current Status:
Anticipate receiving IRZ's 90% designs by the end of the April 2025. Reclamation can then conduct their review.​

Lateral 22.1
Current Status:
Anticipate receiving IRZ's final construction package addressing all comments, by the end of April 2025. A formal acceptance meeting will follow.

Lateral 47.5
Current Status:
Completed; irrigation on the ground to 10,500 acres.

Lateral 80.6
Current Status:
Received the 100% design package on 11/26/2024. Anticipate receiving RH2's response to comments in May 2025.

Lateral 84.7
Current Status:
The first round of comments to the 100% designs has been completed. Anticipate receiving RH2's response to comments in May 2025.
Current Status:
Completed; 5,426 acres converted from deep well irrigation to Columbia River Surface water effectively conserving 16,143 acre-feet (5.3 billion gallons) of water annually in the Odessa Subarea Aquifer.